Government of New Brunswick

Date Project Registered Project Number Proponent Description of the Project Location (county) EIA Specialist Status Date of Decision
2015/01/07 1399 Irishview Estates Ltd. The project involves the construction of the Irishview Estates Subdivision in 10 phases. The proponent is proposing to develop up to185 residential lots on 113 hectares of land located off Route 115, approximately 2.2 km north of the Moncton city limits. Westmorland Crystale Harty Certificate of Determination Issued   2015/09/25
2015/01/12 1400 Havelock Wastewater Collection and Treatment System The proposed project will involve the construction of a new wastewater collection and treatment system. The sewer main will have 145 connections which will extend approximately 6.7 km.   Kings Shawn Hamilton Certificate of Determination Issued 2016/03/15
2015/01/26 1401 McAllister Industrial Park Fertilizer Production Facility The Atlantic Potash Corporation is proposing to construct and operate a potassium nitrate (KNO3) fertilizer production facility in McAllister Industrial Park in Saint John, NB. In total, the facility would have the capacity to produce 180,000 metric tonnes per annum of KNO3 fertilizer. Saint John Shawn Hamilton Determination review in progress  
2015/01/30 1402 City of Saint John The proposed project involves the decommissioning of the Marsh Creek Wastewater Treatment Plant on Thorne Avenue that is no longer used.  The decommissioning includes removal of buildings, lagoon walls, foundations and backfilling. Saint John Lee Swanson Certificate of Determination Issued 2017/05/17
2015/02/18 1403 Trevali Mining Corporation The project includes adding a copper separation circuit within the existing concentrator, expanding the existing storage shed by adding a copper storage/loading building, and adding a transformer station at the Caribou mine site. Restigouche Sheila Goucher Certificate of Determination Issued 2015/05/28
2015/03/03 1404 Department of Education and Early Childhood Development The project consists of decommissioning an existing wastewater treatment lagoon serving the Geary Elementary School, and replacing it with an engineered wetland, followed by sand filter infiltration, in Geary, NB.   Sunbury Crystale Harty Certificate of Determination Issued 2015/06/19
2015/03/18 1405 Glencore Canada Corporation The project consists of a water supply source assessment to develop a new water supply for operations at the Brunswick #12 site Gloucester Sheila Goucher Certificate of Determination Issued   2015/11/10
2015/03/23 1406 Potash Corp NB Division PotashCorp proposes to undertake an expansion of their existing Marine Terminal in Saint John, NB, to accommodate increased potash and salt production related to the Picadilly Expansion Project.     Saint John Shawn Hamilton Determination review in progress  
2015/04/07 1407 Village of Charlo Groundwater Exploration Program – The proponent is proposing to replace an existing back-up water well (located along the Charlo Dam Road) by developing a new well approximately 80 m to the east of the existing one. Restigouche Pierre Doucet Certificate of Determination Issued   2016/01/20
2015/04/20 1408 McLaughlin Hydrocarbon Contaminated Water and Soil Treatment and Disposal The proposed project consists of accepting and subsequently treating hydrocarbon contaminated soil at the McLaughlin Soil Management facility in the Local Service District of Grand Falls. The hydrocarbon contaminated soil would be potentially sourced from New Brunswick, Quebec, Nova Scotia, or Maine. Victoria Shawn Hamilton Certificate of Determination Issued 
2017/12/04
2015/05/19 1409 McCain Foods (Canada) Ltd. Water Supply Source Assessment to test new back-up supply wells for potable water well at the McCain Foods Grand Falls facility. Madawaska Lee Swanson Certificate of Determination Issued   2016/04/29
2015/05/28 1410 Cooke Aquaculture

The project proposes to upgrade the existing wastewater treatment plant at the Oak Bay Hatchery including replacing buildings and the drum filter installation.

The project was expanded in December 2017 to include a Water Supply Source Assessment (WSSA) and a new Genomics Unit. 

Charlotte Lee Swanson Certificate of Determination Issued  
2018/06/29
2015/06/08 1411 New Brunswick Department of Transportation and Infrastructure Stella-Maris-de-Kent Hospital WWTP Upgrade – The proponent is proposing to upgrade its wastewater treatment plant by, among other things, constructing two new aerated cells, decommissioning the existing facultative lagoon, and installing a new outfall pipe. Kent Pierre Doucet Certificate of Determination Issued   2015/09/10
2015/06/08 1412 North Shore MicMac District Council Implementation of a Restoration Design to minimize erosion occurring on the Little Southwest Miramichi River opposite from The Oxbow, Red Bank. Northumberland Lee Swanson Certificate of Determination Issued   2016/06/01
2015/06/24 1413 OSAFE : Organic and Sustainable Altantic Food and Energy Ltd. The development of a 25 acre farm for the production of Pekin ducks, an aquaculture operation for the production of Tilapia fish and a greenhouse for growing organic vegetables year round; to be located on the East side of Grand Lake, NB. Queens Zane Jefferies Certificate of Determination Issued   2015/11/13
2015/07/07 1414 Esgenoôpetitj First Nation  
  
The project involves the construction and operation of a new aerated lagoon to replace the existing system at the Esgenoôpetitj First Nation. The new system will be composed of four aerated cells and include UV disinfection. The effluent pipe will extend into the Inner Miramichi Bay. The project will also include upgrades and new sections to the wastewater collection system and decommissioning of the existing wastewater treatment system. Northumberland Sheila Goucher Certificate of Determination Issued   2016/07/13
2015/07/31 1415 Miscou Fish Product Inc. Back-up Well for Fish Processing Plant – The proponent is proposing to drill and develop a new back-up well for its existing fish processing plant in Miscou. Gloucester Pierre Doucet Certificate of Determination Issued   2016/04/04
2015/08/19 1416 Fisheries and Oceans Canada   Part 2  
Part 3  
The proposed project includes new infrastructure and dredging to take place at the Small Craft Harbour in Back Bay, NB. The project includes construction of a marginal wharf, service area, shore protection and dredging.    Charlotte Shawn Hamilton Determination review in progress  
2015/08/19 1417 Fisheries and Oceans Canada
Part 2  
Part 3  
Alma Dredging and Wharf Repairs/Expansion – The proponent is proposing to dredge near the existing Alma wharf and also undertake repairs and an expansion of the wharf Albert Pierre Doucet Certificate of Determination Issued   2016/02/04
2015/08/26 1418 The Department of Fisheries and Oceans – Small Craft Harbours (DFO-SCH)  
Part 2  
Part 3
The proposed harbor improvement project consists of the construction of a breakwater, modifications to the old ferry wharf, construction of a service area, installation of floating docks and gangway system, and dredging of the east basin in North Head, NB. Charlotte Crystale Harty Certificate of Determination Issued   2015/12/11
2015/08/27 1419 The Department of Fisheries and Oceans – Small Craft Harbours (DFO-SCH)  
Part 2  
Part 3
The proposed harbour improvement project consists of the construction of a breakwater and service area and, dredging of the harbour channel in Leonardville, Fundy NB. Charlotte Sheila Goucher Withdrawn by proponent  
2015/09/08 1420 City of Miramichi   Part 2 Chatham Area Groundwater Exploration – The proponent is proposing to conduct groundwater exploration in the Chatham area in the hopes of developing a new municipal groundwater well. Northumberland Pierre Doucet Certificate of Determination Issued 
2019/02/19
2015/09/24 1421 Kenny’s Development Ltd. The project, River Mist Estates, consists of the development of 44 condominium units in Maugerville, NB with communal water supplies and a communal wastewater disposal system. Sunbury Lee Swanson Approval Denied  
2015/09/29 1422 Town of Woodstock Groundwater Exploration  – The proponent is proposing to conduct groundwater exploration in the Woodstock area in the hopes of developing a new municipal groundwater well. Carleton Rachelle Voisine Certificate of Determination Issued 
2018/04/05
2015/10/01 1423 Prince Edward Island Energy Corporation
Part 2  
Part 3    
The proposed project consists of the installation of two 180 MW submarine cables between Borden, PEI and Cape Tormentine, NB along with approximately 60 km of new transmission line construction between Cape Tormentine and Memramcook.   Westmorland Justin Chase Certificate of Determination Issued   2016/04/15
2015/10/23 1424 Capreit Apartments Inc. Parkside Estates Production Well Replacement – The proponent is proposing to replace a collapsed well that provided drinking water to the 87-lot subdivision located in Lincoln. Sunbury Pierre Doucet Certificate of Determination Issued   2015/12/22